2015-05-12
HMI obtained an important mandate from the City of Montreal for the refurbishment of the high pressure pumping building of the Atwater potable water treatment plant. As part of the 5-year period phased refurbishment project, HMI has been mandated for the installation of 14 new high-pressure pumps and [...]
Read more2015-02-25
On February 27 was held the annual banquet for the engineering graduates of the Université of Moncton. On this occasion, our president, Guy J. Gaudet, was voted past graduate of the year and was selected as the banquet’s honor speaker. The essence of his message to all the [...]
Read more2014-12-15
In mid December 2014, HMI completed all the refurbishment work required on the lifting structures of the spillway at the La Tuque Hydroelectric Generating Station for Hydro-Quebec. Spanned over a total period of 4 years, this mandate also included all the refurbishment required on the embedded parts of [...]
Read more2014-10-06
HMI has obtained the mandate from Hydro-Quebec for the detailed design, supply, installation and commissioning of the spillway gates at the La Romaine 3 Power plant, currently under construction on Quebec’s North Shore. This project also includes the detailed design, supply and installation of the lifting hoists and [...]
Read more2013-05-14
HMI was successfull in obtaining the mandate for the construction of the Index Energy Mills Road cogeneration plant in Ajax, Ontario. This cogeneration facility having an 18 MW capacity in its first phase, will use construction and demolition wood as main fuel. The construction is planned to start in [...]
Read more2012-07-27
HMI was successfull in obtaining the mandate for the rehabilitation of all the intake gates, hoists and draft tube gates of the Beauharnois hydroelectric generating station. Currently in its 5th Phase, the rehabilitation work will be completed by the end of 2017.
Read more2011-03-31
At the prestigious Quebec’s Association of Consulting Engineer’s gala (AICQ) held in Montreal, HMI and AECOM have been awarded the first prize in the industrial project category for the work realized on the modernization of the furnaces of the Quebec City Incinerator. HMI is proud to have worked closely with AECOM’s [...]
Read more