Beauharnois generating station (En cours)

Melocheville, QC

Title 1

HMI has been active since 1995 on the rehabilitation of the intake gates and hoists, as well as the draftube gates of the Beauharnois hydroelectric station.

Title 2

HMI is currently working under the final phase (5) of this strategic rehabilitation project and the present mandate should be completed at the end of 2017.

Le défi

  • Modernize an aging hydroelectric facility by replacing all intake gates and hoists, embedded guides without disruption of service to the client's utilities as well as rehabilitate all draft tubes gates through under water work equipment.

Le résultat

  • Replaced equipment, gates and hoists for turbine intake and draft tubes.
  • Once completed, 144 gates and related equipment would have been rehabilitated.

Valeur

Total for the five phases: $ 192.7 million

Année

1995-2017